- Inspect for compliance with best management practices
- Construction exits and entrances
- Install according to approved plan, if shown.
- Use 1.5″-3.” stone.
- Minimum pad width of 20 feet.
- Minimum pad length of 50 feet.
- Excavate footpring 3 inches.
- If tire washing is required, route runoff from washing to an approved
sediment trap or sediment basin. - Install filter fabric under the entire pad.
- Inspect discharge points and downstream off-site areas for impact.
- Walk the perimeter of the site.
- Inspect active areas.
- Inspect disturbed areas that are not currently being worked.
- Inspect disturbed areas with final stabilization.
- Take into account the overall site.